Minneapolis pauses $5 million Lake Harriet project after complaints

Minneapolis pauses $5 million Lake Harriet project after complaints

Minneapolis had put a $5 million Lake Harriet flood project on hold by Saturday, The Minnesota Star Tribune reported. Residents reported property damage caused by the project work.

Work on the Oliver Avenue South project in the Lynnhurst area began this year and would run through next summer. It was part of a $59 million citywide program to reduce flooding, The Minnesota Star Tribune reported. The work aimed to reduce flooding in south Minneapolis and improve Lake Harriet water quality.

The project would replace old storm sewer pipes that were too small. A large underground box would hold rainwater from storms beneath Oliver Avenue South. By August, the work had stopped while the city studied the design again, The Minnesota Star Tribune reported.

Lake Harriet flood project hit sandy soil

Homeowners warned the city that sandy soil would make digging hard. Jenny Porter said the city promised to test the soil.

When work began, “immediately, it was chaos,” Porter said. The hole grew and its sides collapsed, weakening the boulevard and hurting the sidewalks.

Porter said the city’s goals were “all very noble causes,” but residents received few details.

Porter said shaking from support beams damaged century-old homes and cracked the inside of homes and their foundations. Residents also said they worried about homes sinking and about doors and windows that no longer worked properly. One home had a retaining wall slide several inches, Porter said.

One woman worried about the 104-year-old house she had lived in for 50 years, The Minnesota Star Tribune reported. Dave Keepper, who writes ads and lives on Oliver Avenue, said one homeowner wrote down over 150 cracks in plaster. Keepper also said trees near the project were lost and damaged.

Lake Harriet flood project contract ended

The Minnesota Star Tribune reported that the city and Geislinger & Sons agreed to end the contract. City spokesman Allen Henry gave the reason: “as work on the project was exceeding the scope of the contract.”

The Minnesota Star Tribune reported that public works staff found the original building method could not finish the work. The work could not be completed within the contract scope.

The equipment was removed from the site, Henry said. Residents were told to record damage with photos and file claims that the city would send to the contractor’s insurer. A message left with Geislinger & Sons had not been returned, The Minnesota Star Tribune reported.

Residents first learned through door flyers before work began, The Minnesota Star Tribune reported. The project had been approved years earlier, but residents received no other notice before work began. Dan Patton was a retired finance expert and block leader for the 4900 block of Oliver Avenue South.

Patton said the street never had a flooding problem. Water sometimes pooled when debris collected during extreme rains. Patton wrote, “The scope and scale of the proposed project is unwarranted and wasteful.”

The Lynnhurst neighborhood group asked city officials for a meeting, The Minnesota Star Tribune reported.

The meeting showed that the city would install large catch basins. Patton said the work “all seemed very elective.”

Lake Harriet flood project moves into review

City Council Member Linea Palmisano said Geislinger restored the area for winter. She said the city must do better because it had involved residents too little. She was looking for a new path for the Lake Harriet flood project.

Palmisano said the new path could reduce the project’s size or stop it. City leaders later said some sewer work would still be needed, even if it were smaller, Palmisano said.

Trevor Porter, Jenny Porter’s husband and an engineering director, said residents hit a wall when they sought information. He said the city told residents to use public records requests for plans, shaking limits, tree loss and engineer approval. By late October, he had 10 pending requests, nine awaiting answers for 76 days.

The city hired a firm to handle its messages to the public, Dave Keepper said. He said residents felt “managed and handled rather than like engaged and listened to.”

The Minnesota Star Tribune reported that Keepper called the Lake Harriet flood project a “colossal waste of money.”

Keepper said, “We’re all for government; we don’t have mistrust in government.”

He also said, “I think this is a bit of a wake-up call for all of us.”

Trevor Porter said the neighborhood spent hundreds of hours reading documents and asking questions.

Trevor Porter asked if a neighborhood with those resources struggled to obtain information and influence project direction. He asked, “What happens in neighborhoods that do not possess the same advantages?”

The Lake Harriet flood project remains under a review of whether it can be built, city spokesman Allen Henry said. City officials will meet residents before more work begins, City Council Member Linea Palmisano said.